|
|
| X2H036:
KOMATI RIVER AT KOMATIPOORT:
|
|
|
|
- Access from the
N4 National road and, the road along the
railway are damaged to such an extend that it is
complete inaccessible. The concrete road across
the river towards the weir was still submerged
during the latest observation but, severe damages
could also be expected. Based on previous
reparations done, costs can be as much as R300
000 in order to ensure a proper access to the
weir.
|
- Since the station is
of international importance, the maintenance of
the prescribed operational rules is of essential.
Therefore, the communication systems (satellite
transmission and cell-phone modem) that existed
for the obtaining of real time data before the
flood, should be replaced as soon as possible.
The estimated repair cost amounts to R130 000.
This includes the logger, pressure probe and
mechanical recorder that were also damaged.
|
|
|
| TOTAL AMOUNT ESTIMATED FOR REPARATION: R
2 000 000
|
| |
| |
| |
| X2H016:
CROCODILE RIVER AT TEN BOSCH |
|
|
|
|
- Access road has
been damaged and a stretch of 300 meters needs to
be repaired. Preferable, the road surface must be
treated with a soil-cement mixture to ensure
proper access during all conditions. Costs
involved is estimated at R 80 000.
|
- The station was
equipped with a cell-phone communication system
and was, together with all other measuring
equipment (Logger, probe, cable, mechanical
recorder, solar panel, regulator and modem),
destroyed since it was submerged by more than 3.0
meter of floodwaters. Estimation of costs
involved for the replacement of the equipment is
R 60 000.
|
- Structural damage
could not be evaluated since it was completely
submerged. Conclusions made from photo material
gave an indication of damages on both riverbanks
and reparations could run into thousands.
Depending on the degree of damage, reparations
are estimated at R 150 000. Experience has
learned that the crest irons on the structure are
damaged with every flood and since this will be
no exception, the replacing thereof will
definitely be necessary. Costs is estimated on R
50 000 and will include the repairing of some
concrete erosion.
|
| TOTAL COST ESTIMATION: R 2 500 000
|
|
|
|
| X3H021:
SABIE RIVER AT KRUGER GATE
|
|
|
FLOOD PEAK CALCULATED AT 6
864 M3/S |
|
|
|
- The road to the
station is completely inaccessible and photo
coverage was obtained from a helicopter flight
over the station. Indications from these photos
are that the station has been outflanked on both
sides and will have to be repaired with masses of
soil or alternatively, reinforced concrete walls.
The total cost including reparations to the
access road, is estimated at approximately R 1
000 000.
|
- The international
status of this station requires the availability
of real time data and therefore it was equipped
with a satellite transmission system. Indications
are that this equipment together with the entire
other standard measuring devices were flooded and
destroyed. Replacing all these equipment could
cost as much as R 150 000.
|
- Except for some
erosion damages on the concrete surface of the
structure, not many other damages are suspected.
|
| TOTAL ESTIMATION OF FLOOD DAMAGE: R 600
000
|
|
|
|
| X3H008:
SAND RIVER AT EXETER |
|
|
FLOOD PEAK CALCULATED AT 2
750 M3/S
|
|
|
|
- As in the case
of the Sabie River weir, access to this station
was also not possible but photo coverage obtained
from a helicopter flight, helped to evaluate
possible flood damages. (See photo on next page)
The main issue at this station could be the
repairing of the access road since several
tributaries must be crossed on the way to the
gauging weir. Although tourists use these roads
as well, the Department will have to contribute
to a certain extend, especially in the repairing
of the last 500 meters to the station.
|
|
|
- As one can see from
above photo, no proper evaluation is possible and
assessments are based on conclusions. It is
almost certain that the station is outflanked on
both sides and repair costs could be as much as R
220 000.
|
- Structural
repair works will include the raising of a 150
meter long flank wall and is estimated to be R 70
000.
|
- The station has a
history of silt/sand problems and heavy equipment
will be needed to clean the upstream pool.
Possible cost could be R 50 000.
|
- Instrumentation
consisted of a mechanical recorder, electronic
logger and a cell-phone communication system.
Replacing this equipment will cost approximately
R 50 000.
|
| COST ESTIMATION TO GET STATION
OPERATIONAL AGAIN: R 600 000
|
|
|
|
| X3H006:
SABIE RIVER AT PERRYS FARM
|
|
|
|
|
- The station, which
is situated 20 meters downstream of the bridge,
was by-passed on both banks and besides the
extensive damage to the weir, the recorder hut
was totally demolished. Structural damage to the
rest of the weir is difficult to assess since it
was submerged during the time of observations.
Repairing the flanks will be very costly and is
estimated at R 250 000.
|
- A complete
relocation of the recorder tower will be required
and together with the replacing of the necessary
equipment, costs can be as much as R 200 000.
|
| TOTAL ESTIMATION FOR
REPAIR WORKS: R 450 000
|
|
|
|
| X2H046:
CROCODILE RIVER AT RIVERSIDE |
|
|
|
|
- The station has
a history of being outflanked on the left bank
and huge sums of money were spent to overcome
this problem. The photo clearly indicates that
the problem repeated itself and, in order to
divert the river to the weir, it will require the
construction of a cut-off wall from the weir to
the upstream diversion wall. This wall was
previously constructed in order to direct the
flow towards the weir and a similar method must
be applied. Alternatively, the reconstruction of
the weir at the upstream wall should be
investigated. Civil works to get the station
operational again could be as high as R 1 400
000.
|
- Expensive
communication equipment was installed at this
station since it has both an important
international and operational status regarding
flood warning and water distribution. Therefore,
the station was furnished with expensive
satellite and cell-phone communication systems.
Replacing thereof is essential and will cost
approximately R 120 000.
|
- The exact extent
of the structural damage was difficult to assess
but precautionary measures such as installing
Armour-flex must be taken to ensure the stability
of both flank walls. Cost is estimated at
approximately R 50 000.
|
| TOTAL COST
ESTIMATION FOR REPARATION WORKS: R 1 500 000
|
|
|
|
| X2H059:
WHITE RIVER AT GOEDEHOOP: |
|
|
|
|
- This station was
previously outflanked on the Right Bank and
various precautionary measures were taken to
prevent the repetition thereof. In spite of those
measures, the station was completely outflanked
again, resulting in a complete demolishing of the
right flank cut-off wall. The replacing costs of
the wall will be approximately R 120 000 which is
necessary if measurements are to be continued.
|
- Two recorder
towers were washed away together with R 50 000
worth of instrumentation. The replacing costs
thereof is estimated at R 100 000.
|
| TOTAL ESTIMATED AMOUNT FOR REPARATIONS: R
500 000
|
|
|
|
| X3H011:
MARITE RIVER AT INYAKA (DOWNSTREAM OF INYAKA DAM)
|
|
|
|
|
- Two recorder
towers including instrumentation worth R 65 000
were washed away. The replacement thereof,
including two reinforced concrete towers, could
amount to R 160 000.
|
- Again, an accurate
assessment of structural damages was not possible
during above observation but both riverbanks need
protection against further erosion. Depending on
the area that needs to be protected, the cost
could amount to R 25 000.
|
- The access road is
badly eroded and needs to be treated with a
cement and soil mixture for proper access to the
station at all time. Costs is estimated at R 75
000.
|
|
| TOTAL ESTIMATION FOR REPAIR WORKS: R 50
000 |
|
|
|
| X3H015:
SABIE RIVER LOWER SABIE CAMP (K. N. P.)
|
|
|
FLOOD PEAK CALCULATED AT
12 000 M3/S
|
|
|
|
- Both the left and
Right Bank recorder towers were flooded,
resulting in the complete destruction of the
electronic logger and mechanical recorder. The
100 meters vented data cable connected to the
logger was swept away and must be replaced. Since
the electronic equipment consisted of an OTT-log
and compliant equipment, the estimated replacing
costs can be as much as R 82 000.
|
- Although damages
on the Right Bank are still difficult to assess,
recent photo coverage indicated a definite damage
of the left bank and the Armour-flex protection
must be replaced. Depending on the damaged area,
a preliminary cost estimation is in the order of
R 100 000.
|
- Further structural
damage is not yet possible to assess but,
indications are that the stilling well for the
probe is broken and must be replaced. Possible
cost is estimated at R 24 000
|
| TOTAL ESTIMATION FOR REPAIR WORKS: R 800
000
|
|
|
|
| X3H004:
NORTH SAND RIVER AT DE RUST (HAZYVIEW)
|
|
|
|
|
- The recorder tower
including measuring instrumentation worth R 26
000 are washed away.
|
- Exact structural
damage is not yet possible to assess but
indications are that the station has been
outflanked on both sides. Reparation costs can be
as much as R 60 000 including erosion protection
and the replacing of certain damaged sections of
the gauging weir.
|
- The recorder tower
will have to be raised by approximately 2.0
meters to limit future damage of expensive
instrumentation may cost a additional R 60 000.
|
- The national Road
Bridge was also by-passed on both sides but must
be repaired by the Provincial Roads Department.
|
| TOTAL ESTIMATED REPAIR COST: R200 000
|
|
|
| FLOOD DAMAGES IN THE CATCHMENT OF THE UPPER
ELEPHANTS RIVER
|
|
|
| B2H015:
WILGE RIVER AT ZUSTERSTROOM:
|
|
- The recorder tower
was flooded and the electronic instrumentation
was damaged beyond repair. Replacing the
equipment will cost R 20 000.
|
- Raising the tower
by 2.0 meters and replacing the existing steel
hut with a reinforced concrete hut, will cost
approximately R50 000.
|
|
| TOTAL ESTIMATED COSTS: R 70 000
|
|
|
|
|
| B3H017:
ELEPHANTS RIVER AT LOSKOP DAM (DOWN STREAM
|
|
- The access bridge
to the recorder tower was washed away and must be
replaced. Estimated costs is R 32 000. The
instrumentation was also damaged and will cost R
22 000 to be replaced.
|
|
| TOTAL ESTIMATED REPAIR COST: R 54 000
|
|
|
| PRELIMINARY ESTIMATION OF THE
TOTAL DAMAGES CAUSED BY THE RECENT FLOODS CAN BE
SUMMARIZED AS FOLLOWS:
|
|