B. GRONDOPMETINGS
TAAK OPDRAG LêER NO. STREEF BESKRYWING % DATUM
NO DATUM   DATUM   VOLTOOI VOLTOOI
01/96   18/2/C110   Ermelo steenkoolmyne:  Toets- 0  
        opmeting (Lae prioriteit)    
153/96 27/09/96 18/2/X220   Witklip dam:  Cross-sections 50 uitgestel
116/97 11/07/97 18/2/B230   Kwandebele region water supply 70 Konstruksie
        augmentation scheme: Bronk-   uitgestel
        horstspruit raw water rising main    
        from pump station to water treat    
        ment palnt (WTP)    
        Nellshoogte uitkoop bakens 90  
77/98 23/03/98 18/2/T200   Mtata dam: Base plan for dam 50 uitgestel
        zoning and back water calcula-    
        tions    
        Oorskakeling van boot na GPS 99  
339/98 26/10/98 18/2/X310   Sabie river GWS: First Phase: 0 Afgestel
        Injaka dam: Staff housing site lay-    
        out drawings    
             
01/04/99 - 31/03/2000
557/99 27/09/99 18/2/G100   Riviersonderend - Berg river GWS: 100 31/03/2000
        Survey requirement:  Survey Control    
708/99 13/12/99 18/2/B710??   Olifants-Sand water transfer scheme: 0  
        Feasibilty of further phases    
         
01/04/2000 - 31/03/2001
B. GRONDOPMETINGS
TAAK OPDRAG LêER NO. STREEF BESKRYWING % DATUM
NO DATUM   DATUM   VOLTOOI VOLTOOI
07/2000 07/04/2000 18/2/A910   Vondo regional WSS:  Flood damage 100 31/05/2000
        downstream of Vondo dam:  Site survey    
11/2000 20/04/2000 18/2/T600 W7421: Eastern Pondoland Basin Study 0  
      Request to provide basin surveys for    
      two proposed dams in the Lusikisiki    
        region (Zalu & Lusikisiki dams)    
362/2000 03/07/2000 18/2/B730   Olifants river :  Massingir dam basin 0  
        survey    
504/2000 01/08/2000 18/2/A910   Luvuhu river GWS:  Survey of pipeline 100 31/10/2000
        route from reservoir NR3 to Malamulele     
564/2000 28/08/2000 18/2/B900   Mutale river GWS:  Mutale Weir:  Sur- 0  
        vey for the new wier site    
643/2000 04/10/2000 18/2/B710   Mutale GWS: Mutale weir:  Survey of 100 31/10/2000
        diamond boreholes    
B. GRONDOPMETINGS
TAAK OPDRAG LêER NO. STREEF BESKRYWING % DATUM
NO DATUM   DATUM   VOLTOOI VOLTOOI
722/2000 10/11/2000 18/2/C310   Mooifontein plantasie:  Noord-wes pro    
    18/4/3/2/401/5   vinsie:  vasstel van fotobeheer 100 30/11/2000
851/2000 01/04/2000 18/2/T200   Mhlahlane Forest:  Survey of addsional 100 30/04/2000
        boundary beacaons    
852/2000 01/06/200 18/2/B810   Magoebaskloof:  height determination 100 30/06/2000
        of trees    
853/2000 01/06/2000 18/1   Supplying of sediment plans and re- 100 30/06/2000
        ports for BKS    
854/2000 01/06/2000 18/2/T310   Planimeter for capacity determination of 100 30/06/2000
        4 Eastern Cape dams Mbeleni,Tender-    
        gate,Majola, and Boesmanskranz    
855/2000 01/09/2000 18/2/A610   Nylsvlei:  Fixing of gauge plates 100 30/09/2000
        phase 1    
856/2000 01/04/2000 18/2/D110   LHWP crustal GPS monitoring 100 31/12/2000
             
B. GPS
  TASK 0% 1%-99% 100% TOTAAL
APR 3 4 7 1 15
MEI 0 4 6 1 11
JUN 3 5 5 3 16
JUL 1 5 5 0 11
AUG 2 6 6 0 14
SEPT 1 6 6 1 14
OKT 1 6 5 2 14
NOV 1 6 5 1 13
DES 0 6 5 1 12
JAN          
FEB          
MRT          
APR